Corp Memberscheme

0%
0 votes, 0 avg
1565

Welcome to the Examination Portal.  We wish you all the best as you kick start a wonderful career with us

ONLINE EXAMINATIONS

The online assessment is taken on completion of the training material. You will be asked 100 multiple-choice questions with a pass mark of 50%. The answers are marked automatically so you will instantly know whether you have passed. If you don’t pass don’t worry! You can take the Exam again

Whether you are a student on our platform or not we encourage you to email your enquires to our friendly team if you need help with anything at info@corpmemberscheme.com

REGISTER TO START YOUR EXAMINATION

1 / 100

CP.  Dayo the project manager for a construction project worked on a Matrix to assign resources to work packages. He made use of called RACI.

Which of these is accurate?

2 / 100

 

CP. What are the different stages of team development?

3 / 100

CP. Collins had a disagreement with James, his colleague. This impacted the project deliverables by 2 extra days. When the project manager knew about the conflict he gave the both of them a deadline to do the pending work. What method of conflict resolution did he adopt?

4 / 100

CP. The Federal Government of Nigeria has agreed to construct a bridge between Idoko Town and Kijani Town. The people of the different Towns have to travel four hours to trade. However, this development will aid the Government boost GDP. Why was this project initiated?

5 / 100

CP. Tobi is managing a project were she controls the budget. What organisational structure is she operating in?

6 / 100

CP.  At the Project Site, the team members had an intense argument on who was to use the pool car for their project activities. The project manager called for a meeting to understand their needs after which he prioritized them. What method of conflict resolution did he use?

7 / 100

CP. In a power-interest grid, how do you manage a stakeholder with High power and High Interest

8 / 100

CP. How many percent of time does a project manager spend communicating?

 

9 / 100

CP. Which of the statements is correct?

10 / 100

CP.  In 2018, a road construction project was initiated by KYZ firm. During Execution the project was abruptly brought to a close. It was gathered that the Director of road works was not pleased with the execution plan because the alternative route could not be plied by motor vehicles. What do you think was the issue?

11 / 100

CP.  Adeleke is a project manager with team members in Brazil, England and Nigeria. As an experienced project manager, what is the most important advice you will give?

12 / 100

CP. Dayo is a project manager who started his project with 50 team members, during execution, six people were added to the team. Due to some internal conflict at the close of the project a team member left. How many communication channels were added at execution stage?

13 / 100

CP. Which of these is not a process in Risk management?

14 / 100

CP. In a power-interest grid, how do you manage a stakeholder with Low power and High Interest

15 / 100

Your company wants to decide between Investment A, which will cost $200K upfront, and Investment B, which will cost $250K upfront. If the economy performs well, Investment A will bring in $1m for your company, but if the economy performs poorly, then it will lose $500K for your company. If the economy performs well, Investment B will bring in $1.5m for your company, but if the economy performs poorly, then it will lose $400K for your company. There窶冱 a 60% chance of a strong market and a 40% chance of a weak market.

USE THIS QUESTION TO ANSWER THIS AND THE NEXT.

What is EMV A?

16 / 100

CP.  What is EMV B?

 

17 / 100

CP. ABC company needs to transport some glass furniture for a construction work, due to the sensitivity of the work. The project manager hired another organization to transfer the glass furniture. What strategy was used?

18 / 100

CP. Akintunde was upset with the behaviour of his team members, he gave a speech on how team members should conduct themselves, what method of communication did he use?

19 / 100

CP. In a team of 29 how many communication channels are they?

20 / 100

CP. Which is out of place

21 / 100

CP. Which of the following is not the description of a 窶弃roject

22 / 100

CP. Which is the best description of a successful project

23 / 100

CP.  Answer Yes or No.

Project is a means of achieving organization,s strategic plan.

24 / 100

CP. In Contract management, what is the best form of specification.

25 / 100

CP. what best describes the cause of Conformance

26 / 100

CP. What best describes the cost of Nonconformance

27 / 100

CP. What is the best way to guide against waste of Quality

28 / 100

CP.

what are the best way to measure Quality performance

29 / 100

CP. What are the input ingredients for Quality Assurance

30 / 100

CP.  What is the main use of  “Fish Bone”analysis in project management.

31 / 100

CP. What best describes the objectives of a quality audit (Pick ass appropriate)

32 / 100

CP. ,Payment on fixed price is:

33 / 100

CP. Cost – reimbursable contract  is:

34 / 100

CP. What are the best  quality of a Project Manager.

35 / 100

CP.  The essentials of Project management involve are

36 / 100

Dayo the project manager for a construction project worked on a Matrix to assign resources to work packages. He made use of called RACI.

Which of these is accurate?

37 / 100

What are the different stages of team development?

38 / 100

  1. Dayo heads a team in ABC organisation; they are responsible for delivering gift items to different locations in the country. In an interview, he explained his role as a project management role. Which statement is correct

39 / 100

  1. The Triple constraint is made up of

40 / 100

  1. The Federal Government of Nigeria has agreed to construct a bridge between Idoko Town and Kijani Town. The people of the different Towns have to travel four hours to trade. However, this development will aid the Government boost GDP. Why was this project initiated?

41 / 100

  1. Tobi is managing a project were she controls the budget. What organisational structure is she operating in?

42 / 100

  1. Adeleke is a project manager with team members in Brazil, England and Nigeria. As an experienced project manager, what is the most important advice you will give?

43 / 100

  1. At the Project Site, the team members had an intense argument on who was to use the pool car for their project activities. The project manager called for a meeting to understand their needs after which he prioritized them. What method of conflict resolution did he use?

44 / 100

  1. In a power-interest grid, how do you manage a stakeholder with High power and High Interest

45 / 100

 

  1. Which of the statements is correct?

46 / 100

  1. In 2018, a road construction project was initiated by KYZ firm. During Execution the project was abruptly brought to a close. It was gathered that the Director of road works was not pleased with the execution plan because the alternative route could not be plied by motor vehicles. What do you think was the issue?

47 / 100

 

  1. Adeleke is a project manager with team members in Brazil, England and Nigeria. As an experienced project manager, what is the most important advice you will give?

48 / 100

  1. In a power-interest grid, how do you manage a stakeholder with High power and High Interest

49 / 100

  1. In a power-interest grid, how do you manage a stakeholder with Low power and High Interest

50 / 100

  1. ABC company needs to transport some glass furniture for a construction work, due to the sensitivity of the work. The project manager hired another organisation to transfer the glass furniture. What strategy was used?

51 / 100

Which of these is not a factor to be considered when choosing communication technology?

52 / 100

Akintunde was upset with the behaviour of his team members, he gave a speech on how team members should conduct themselves, what method of communication did he use?

53 / 100

  1. Which is out of place

54 / 100

Which of the following is not the description of a 窶弃roject

55 / 100

Which is the best description of a successful project

56 / 100

Answer Yes or No.

Project is a means of achieving organization,s strategic plan.

57 / 100

Mention the highest Risk in project Management

58 / 100

In Contract management, what is the best form of specification.

59 / 100

what best describes the cause of Conformance

60 / 100

what best describes the cost of Nonconformance

61 / 100

,What is the best way to guide against waste of Quality

62 / 100

what are the best way to measure Quality performance

63 / 100

What are the input ingredients for Quality Assurance

64 / 100

What is the main use of  “Fish Bone”analysis in project management.

65 / 100

What are the principal attribute of Procurement in Project

66 / 100

What best describes the objectives of a quality audit (Pick ass appropriate)

67 / 100

What are the best process of Project management.Procurement

68 / 100

,Payment on fixed price is:

69 / 100

What are the best  quality of a Project Manager.

70 / 100

The essentials of Project management involve are

71 / 100

Group of related projects managed in a ------------ way to obtain benefits and control

72 / 100

Why do we initiate project?

73 / 100

what is the most important phase in a project cycle.

74 / 100

The most important determinant factor in the number of phases in a project is:

75 / 100

what is the most difficult phase in a project cycle.

76 / 100

,  The determinant factor in the selection of  the staff of a project will depend on:

77 / 100

When is the adjourning time for a project

78 / 100

What is a major variable that can cause project delay

79 / 100

Which department had the major responsibility for recruiting the staff for a project ?

80 / 100

………….. department is responsible for sourcing and monitoring the  delivery of materials for a project.

81 / 100

-------------- had the MAJOR  responsibility for ensuring that the project is completed within the cost budget, quality and the timing.

82 / 100

What is the major description of McGregor Theory X

83 / 100

------------- Manager should provide challenging assignments to ream members and provide recognition for high performance

84 / 100

The major responsibility of the project team is to monitor .

85 / 100

Project Performance Appraisal is achievable through:

86 / 100

what are the characteristics of Conflict Management in Project

87 / 100

Conflict resolution is always difficult due to the following:

88 / 100

The best  techniques for resolving conflicts are:

89 / 100

In order to achieve the best service from the supplier, the best sourcing technique is

90 / 100

, In starting a project meeting, what is the best item (agenda) that should come firstA, safety talk

91 / 100

In Manslow,s hierarchy, which item can be classified as 窶徭elf esteem

92 / 100

What can you classify as the Project Manager,s role in Procurement?

93 / 100

What is E – procurement?

94 / 100

What is the most favoured contracting system by buying organisations?

95 / 100

Mention the processes of Stakeholder management

96 / 100

Mention the starting point of Stakeholder management processes

97 / 100

For a project to be successful in a community, you require the following:

98 / 100

Rather than use Triangular Distribution while doing Three Point Estimation you choose to use Beta Distribution. Based on your analysis and understanding you are confident that the project would be completed with a total cost of 108,000 $. You also estimate that a best case estimate would be 90000 $ while a worst case scenario would result in the costs incurred to shoot up to 138000 USD. What would the Three point Cost estimate be using Beta Distribution?

99 / 100

CFM1. People negotiate daily, often without considering it a negotiation

100 / 100

Question - 14 You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is process you are working on ?